I have created project plan which has finished date 20-Dec-2017. In project professional when i close all subtask than project professional show finished date 20-Dec-2017.
In my project plan at the end give one blank line and add some project support task which ends in 10-march-2018. than i publish project.
Problem is that on Project Online it show finished date 10-march-2018 instead of 20-Dec-2017. pls guide why this difference and project online not showing finish date as 20-Dec-2017.
pls guide.